VERONA, NJ – Verona has until late March to put its Fairview Avenue well back into service under a state consent order, Township Manager Kevin O'Sullivan told the Town Council on Monday. The well has been offline for more than five years because of PFAS contamination.
O'Sullivan said a force majeure extension from the state moved the compliance date to about March 22 or 25, 2027. He said the contractor is still scheduled to finish in January or February, ahead of both its contract and the consent order schedule.
Some equipment is late. O'Sullivan said the contractor has most of what it needs and is installing it, but a couple of valves have been delayed.
Sign Up for FREE Verona/Cedar Grove Newsletter
Get local news you can trust in your inbox.
Councilwoman Christine McGrath, who asked for the date, said the project had been "delayed and delayed again." When O'Sullivan gave the March window, she replied, "It's getting a little tight." O'Sullivan agreed.
He said the contractor knows the deadline and has been told it would owe liquidated damages if it misses the completion date. It is the same firm that just finished the Claridge Drive pump station, which went into service this week.
Five years of moving targets
If the new schedule holds, the well will return about two years after the township first said it would. Verona took the well offline on July 28, 2021, after a June 30 sample showed PFOA above the state drinking water limit. Since then the town has bought all of its water from the Passaic Valley Water Commission, according to a 2023 township notice.
The parkland designation was flagged early as a drag on the schedule. Engineers told the council in 2022 that the Green Acres encumbrance on the Fairview site would delay permitting.
Verona's other well, on Linn Drive, finished its upgrade in early 2025. The township has said it will keep using Passaic Valley water until all of the rehabilitation is complete.
What it costs, and what's next
The price has grown well past the first estimate. When the problem surfaced in 2021, officials put the cost of filtering both wells at about $1 million. Fairview alone is now backed by the $3.6 million Water Bank loan.
Residents are already paying for the work. A rate plan the council adopted in 2024 added a PFAS remediation surcharge to water bills starting in 2025.
The state's infrastructure bank covered most of the Linn Drive job. A $2 million grant left Verona responsible for $262,337 of the $2,262,337 cost, and the township said it expected similar help for Fairview, according to a 2024 township water notice. The final Fairview figures have not been announced.
The well is on Hillwood Terrace, near the Hillwood senior apartments. Engineers designed it to pump 500 gallons a minute into the low-pressure section of the water system, according to a 2022 Jacobs presentation.
McGrath also asked about the Claridge Drive pump station. O'Sullivan said crews are checking the system upstream and downstream as pressure increases there, which answers her question about retesting hydrant pressure. He expects that project to close out in December.
The township's next water milestone is earlier. Its Phase 2 watershed improvement assessment is due to the state by the end of December, and O'Sullivan said a draft is expected this month.